Marbello Project: Progress as of the beginning of March 2011

We have almost finished the exterior on the entire container home. The radiant barrier has been working better than expected. It feels at least 15 degrees Fahrenheit cooler than it did before, even when the sun is directly on the containers.

We had another delivery of tires for the tire retaining wall, and we hope to get another load next week. We currently have enough to get us at least four feet higher on the wall. Along with the tires, the gutters for the water catchment system were delivered today.

We have been working on the layout and cabinet designs for the kitchen. Pictures will be posted soon.